United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Arizona (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown22,100 MW
Active in queue7,437 MW7 requests
Agreement signed5,087 MW4 requests
Withdrawn207,398 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q255, Coconino County
Solar + storage
2,000 MWIn study Coconino, AZWest May 2017target 2021
Solar + storage project Q256, Pinal County
Solar + storage
100 MWIn study Pinal, AZWest May 2017target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)