πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Alabama (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5442 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn5442 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-317, Lowndes County
Solar
150 MWWithdrawn / abandoned Lowndes, ALSoutheast Oct 2013
Onshore wind project IC-323, Cleburne County
Onshore wind
88.4 MWWithdrawn / abandoned Cleburne, ALSoutheast Nov 2013
Onshore wind project IC-287, Etowah County
Onshore wind
80.5 MWWithdrawn / abandoned Etowah, ALSoutheast Mar 2013
Solar project IC-306, Montgomery County
Solar
75.0 MWWithdrawn / abandoned Montgomery, ALSoutheast Jun 2013
Hydro project IC-319, Marengo County
Hydro
48.0 MWWithdrawn / abandoned Marengo, ALSoutheast Oct 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)