United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in West (non-ISO utilities) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown263,861 MW
Active in queue21.7 GW72 requests
Agreement signed3,861 MW26 requests
Withdrawn24741.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

26 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 82, Meagher County
Onshore wind
600 MWAgreement signed Meagher, MTWest Feb 2019
Solar + storage project IA-PNM-2019-11, San Juan County
Solar + storage Β· 450CT 8ME
500 MWAgreement signed San Juan, NMWest Apr 2019target 2025
Solar + storage project Q310, Yuma County
Solar + storage
450 MWAgreement signed Yuma, AZWest Aug 2019target 2023
Onshore wind project 83, Meagher County
Onshore wind
300 MWAgreement signed Meagher, MTWest Mar 2019
Solar + storage project 573, Power County
Solar + storage Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Power, IDWest Nov 2019target 2027
Solar + storage project Q295, Pinal County
Solar + storage
250 MWAgreement signed Pinal, AZWest Mar 2019target 2022
Solar + storage project Company 181, Clark County
Solar + storage
200 MWAgreement signed Clark, NVWest Sep 2019target 2028
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Battery storage project IA-PNM-2019-19, Bernalillo County
Battery storage Β· PNM β€šΓ„Γ¬ Generation
150 MWAgreement signed Bernalillo, NMWest Apr 2019target 2021
Solar project 558, Jerome County
Solar Β· Cat Creek Energy, LLC
120 MWAgreement signed Jerome, IDWest May 2019target 2026
CO100SB Project
Solar + storage
100 MWAgreement signed Otero, NMWest Mar 2019target 2027
Solar + storage project Company 174, Clark County
Solar + storage
100 MWAgreement signed Clark, NVWest Mar 2019target 2023
VE100S Project
Solar + storage
100 MWAgreement signed Dona Ana, NMWest Sep 2019target 2026
Battery storage project Company JW, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2019target 2027
Solar + storage project IA-PNM-2019-05, Santa Fe County
Solar + storage
96.0 MWAgreement signed Santa Fe, NMWest Apr 2019target 2021
Solar + storage project TCS-44, Crook County
Solar + storage Β· Three Springs Interconnection B LLC
80.0 MWAgreement signed Crook, ORWest Sep 2019target 2027
Solar project QF19-081, Jefferson County
Solar
53.0 MWAgreement signed Jefferson, ORWest Nov 2019target 2022
Battery storage project Company JV, Carson City County
Battery storage
50.0 MWAgreement signed Carson City, NVWest Mar 2019target 2023
VE50S Project
Solar + storage
50.0 MWAgreement signed Dona Ana, NMWest Sep 2019target 2026
Solar + storage project TCS-45, Crook County
Solar + storage Β· Three Springs Interconnection C LLC
40.0 MWAgreement signed Crook, ORWest Sep 2019target 2028
Solar + storage project TCS-43, Crook County
Solar + storage Β· Three Springs Interconnection A LLC
40.0 MWAgreement signed Crook, ORWest Sep 2019target 2027
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023
Hydro project 1186, Bannock County
Hydro Β· Commercial Energy Management, Inc.
0.9 MWAgreement signed Bannock, IDWest Oct 2019target 2021
Solar project TCS-40, Benton County
Solar Β· Oregon State University
0.8 MWAgreement signed Benton, ORWest Jul 2019target 2024
Solar project TCS-38, Benton County
Solar Β· Oregon State University
0.3 MWAgreement signed Benton, ORWest Jul 2019target 2024
Solar project TCS-39, Benton County
Solar Β· Oregon State University
0.2 MWAgreement signed Benton, ORWest Jul 2019target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)