United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nebraska, West

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown156,013 MW
Active in queue300 MW1 requests
Agreement signed300 MW1 requests
Withdrawn156,013 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2018-18, Banner County
Onshore wind
1,000 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-1405, Banner County
Onshore wind
600 MWWithdrawn / abandoned Banner, NEWest Jun 2014target 2016
Onshore wind project GI-2018-17, Banner County
Onshore wind
502 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-16, Banner County
Onshore wind
502 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-10, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-7, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-12, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-8, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-14, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-13, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-15, Banner County
Onshore wind
300 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-0816, Scotts Bluff County
Onshore wind
204 MWWithdrawn / abandoned Scotts Bluff, NEWest Jul 2008target 2010
Onshore wind project GI-0815, Cheyenne County
Onshore wind
204 MWWithdrawn / abandoned Cheyenne, NEWest Jul 2008target 2010
Onshore wind project GI-2018-11, Banner County
Onshore wind
199 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-9, Banner County
Onshore wind
199 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)