Coal interconnection queue in Southeast (non-ISO utilities)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8180 MW
Active in queue180 MW8 requests
Agreement signed0.0 MW0 requests
Withdrawn2315.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project GI-48, Randolph County
Coal
33.0 MWIn study Randolph, MOSoutheast Oct 2012target 2012
Coal project 978035, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Coal project 978034, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Coal project GI-43, Randolph County
Coal
28.2 MWIn study Randolph, MOSoutheast Nov 2009target 2012
Coal project GI-40, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Coal project GI-39, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Coal project GI-41, Randolph County
Coal
17.0 MWIn study Randolph, MOSoutheast Oct 2009target 2012
Coal project GI-42, Randolph County
Coal
1.7 MWIn study Randolph, MOSoutheast Nov 2009target 2010

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)