United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Southeast (non-ISO utilities) (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown260.0 MW
Active in queue35.0 GW178 requests
Agreement signed9,901 MW23 requests
Withdrawn19532.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 345, Polk County
Gas Β· Duke Energy Florida, LLC
40.0 MWOperating Polk, FLSoutheast Jan 20242025
Battery storage project 114, Hillsborough County
Battery storage
20.0 MWOperating Hillsborough, FLSoutheast Oct 2024target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)