United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Southeast (non-ISO utilities) (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7892 MW
Active in queue619 MW3 requests
Agreement signed2.0 MW1 requests
Withdrawn494,719 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 8598, Buncombe County
Gas Β· Duke Energy Progress, LLC
280 MWOperating Buncombe, NCSoutheast Dec 20152019
Gas project 8597, Buncombe County
Gas Β· Duke Energy Progress, LLC
280 MWOperating Buncombe, NCSoutheast Dec 20152019
Gas project 162
Gas
108 MWOperating Southeast Feb 20152019
Solar project 9452
Solar Β· Masked
75.0 MWOperating Southeast Jun 20152018
Solar project 168
Solar Β· FPL
74.5 MWOperating Southeast Feb 20152020
Solar project 9637
Solar Β· Monroe Solar Farm
60.0 MWOperating Southeast Apr 20152017
Gas project 269, Sumner County
Gas
14.0 MWOperating Sumner, TNSoutheast May 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)