United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Mississippi, Southeast

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,445 MW
Active in queue4,211 MW28 requests
Agreement signed1,445 MW12 requests
Withdrawn17660.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 423, Clay County
Solar
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2026
Battery storage project 429, Clay County
Battery storage
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2028
Solar project 466, Clay County
Solar
200 MWAgreement signed Clay, MSSoutheast Feb 2021target 2028
Solar project IC-1145, Jasper County
Solar
156 MWAgreement signed Jasper, MSSoutheast Jun 2023target 2028
Solar project 425, Chickasaw County
Solar
150 MWAgreement signed Chickasaw, MSSoutheast Apr 2020target 2027
Solar project 422, Chickasaw County
Solar
145 MWAgreement signed Chickasaw, MSSoutheast Apr 2020target 2027
Solar project 313, Monroe County
Solar
100 MWAgreement signed Monroe, MSSoutheast May 2017target 2026
Solar + storage project 530, Pinola County
Solar + storage
90.0 MWAgreement signed Pinola, MSSoutheast Mar 2023target 2028
Solar project 314, Monroe County
Solar
60.0 MWAgreement signed Monroe, MSSoutheast May 2017target 2021
Solar project 519, Marshall County
Solar
50.0 MWAgreement signed Marshall, MSSoutheast Sep 2022target 2029
Battery storage project 424, Clay County
Battery storage
50.0 MWAgreement signed Clay, MSSoutheast Apr 2020target 2026
Solar project IC-1203, Jasper County
Solar
44.0 MWAgreement signed Jasper, MSSoutheast Nov 2023target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)