United States βΊ Grid βΊ Interconnection queues βΊ Indiana
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Indiana, Southeast
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project LGE-GIS-2022-005, Clarke County Solar + storage |
1,400 MW | Withdrawn / abandoned |
| Solar + storage project LGE-GIS-2022-006, Clarke County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Battery storage project LGE-GIS-2021-024, Floyd County Battery storage |
200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)366 Β· 71.5 GW
- PJM (Mid-Atlantic, Midwest)210 Β· 40.3 GW
- Southeast (non-ISO utilities)3 Β· 2,600 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)