United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Indiana, Southeast

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32,600 MW
Active in queue500 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn32,600 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project LGE-GIS-2022-005, Clarke County
Solar + storage
1,400 MWWithdrawn / abandoned Clarke, INSoutheast Jul 2022target 2029
Solar + storage project LGE-GIS-2022-006, Clarke County
Solar + storage
1,000 MWWithdrawn / abandoned Clarke, INSoutheast Aug 2022target 2029
Battery storage project LGE-GIS-2021-024, Floyd County
Battery storage
200 MWWithdrawn / abandoned Floyd, INSoutheast Oct 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)