Interconnection queue in Texas, SPP (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61,367 MW
Active in queue1,367 MW6 requests
Agreement signed1,367 MW6 requests
Withdrawn245,371 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-239, Yoakum County
Solar
300 MWAgreement signed Yoakum, TXSPP Nov 2017target 2026
Onshore wind project GEN-2017-151, Crosby County
Onshore wind
300 MWAgreement signed Crosby, TXSPP Nov 2017target 2026
Onshore wind project GEN-2017-158, Parmer County
Onshore wind
265 MWAgreement signed Parmer, TXSPP Nov 2017target 2026
Solar project GEN-2017-040, Ochiltree County
Solar
200 MWAgreement signed Ochiltree, TXSPP May 2017target 2026
Onshore wind project GEN-2017-146, Castro County
Onshore wind
152 MWAgreement signed Castro, TXSPP Nov 2017target 2026
Solar project GEN-2017-187, Terry County
Solar
150 MWAgreement signed Terry, TXSPP Nov 2017target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)