Interconnection queue in Arkansas, SPP (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3400 MW
Active in queue400 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn111,765 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2022-130, Sebastian County
Battery storage
200 MWIn study Sebastian, ARSPP Feb 2023target 2030
Solar project GEN-2023-132, Craighead County
Solar
150 MWIn study Craighead, ARSPP Oct 2023target 2028
Battery storage project GEN-2023-206, Sebastian County
Battery storage
50.0 MWIn study Sebastian, ARSPP Oct 2023target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)