OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in PJM (Mid-Atlantic, Midwest) (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AH1-672, Sussex County Solar Β· TerraForm Freeman Solar, LLC |
75.0 MW | In study |
| Battery storage project AG2-380, Queen Anne's County Battery storage Β· Concho Solar I, LLC |
20.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)436 Β· 104.7 GW
- MISO (Midcontinent)290 Β· 62.9 GW
- West (non-ISO utilities)192 Β· 45.5 GW
- Southeast (non-ISO utilities)178 Β· 35.0 GW
- SPP (Southwest Power Pool)81 Β· 18.0 GW
- NYISO (New York)89 Β· 15.6 GW
- ISO-NE (New England)15 Β· 3,285 MW
- PJM (Mid-Atlantic, Midwest)2 Β· 95.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)