United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in PJM (Mid-Atlantic, Midwest) (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown62,680 MW
Active in queue2,928 MW7 requests
Agreement signed2,680 MW6 requests
Withdrawn23127.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Trumbull Energy Center
Gas
940 MWAgreement signed Trumbull, OHPJM Oct 2015target 2026
Sullivan Generating Station 1
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Sullivan Generating Station 2
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Glen Falls Facility
Gas
550 MWAgreement signed Harrison, WVPJM Apr 2015target 2029
Mountaineer #1
Coal
36.0 MWAgreement signed WVPJM Oct 20152018
Cedar Lane Solar
Solar
4.0 MWAgreement signed Queen Anne's, MDPJM Oct 2015target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)