Completed queue projects in MISO (Midcontinent) (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown71,087 MW
Active in queue28.0 MW2 requests
Agreement signed28.0 MW2 requests
Withdrawn216,395 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J238, Morgan County
Gas
725 MWOperating Morgan, INMISO Jan 20122018
Onshore wind project J249, Dickey County
Onshore wind
180 MWOperating Dickey, NDMISO Jul 20122012
Onshore wind project G934, Gratiot County
Onshore wind
150 MWOperating Gratiot, MIMISO Jan 20122020
Other project J242, Macomb County
Other
12.8 MWOperating Macomb, MIMISO May 20122016
Gas project J256, Marshall County
Gas
8.0 MWOperating Marshall, INMISO Oct 20122015
Onshore wind project J246, Gratiot County
Onshore wind
7.0 MWOperating Gratiot, MIMISO May 20122015
Hydro project J241, Florence County
Hydro
3.7 MWOperating Florence, WIMISO Apr 20122016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)