United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Texas, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31,246 MW
Active in queue6,659 MW27 requests
Agreement signed332 MW3 requests
Withdrawn7015.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J472, Montgomery County
Gas
1,045 MWOperating Montgomery, TXMISO Sep 20152020
Solar project J1030, Polk County
Solar
150 MWOperating Polk, TXMISO Mar 20182023
Gas project J486, Grimes County
Gas
51.0 MWOperating Grimes, TXMISO Oct 20152000

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)