United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in CAISO (California) (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown93,749 MW
Active in queue16.3 GW41 requests
Agreement signed12.6 GW32 requests
Withdrawn10746.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Arida 3 Solar Farm
Solar + storage
900 MWIn study Clark, NVCAISO Apr 2020target 2030
Sunrise Power Improvement
Gas
656 MWIn study Kern, CACAISO Apr 2020target 2024
Harquahala Sunrise
Solar + storage
618 MWIn study Maricopa, AZCAISO Apr 2020target 2030
Hawkins Solar Hybrid
Solar + storage
500 MWIn study Kern, CACAISO Apr 2020target 2027
Sequoia
Solar + storage
400 MWIn study Tulare, CACAISO Apr 2020target 2031
Commerce Energy Storage 2
Battery storage
250 MWIn study Los Angeles, CACAISO Apr 2020target 2026
Puff Hybrid Solar
Solar + storage
204 MWIn study Kern, CACAISO Apr 2020target 2030
Conaway Hybrid Power Plant
Solar + storage
170 MWIn study Yolo, CACAISO Apr 2020target 2023
Scafell Storage
Battery storage
52.0 MWIn study San Diego, CACAISO Apr 2020target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)