United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in CAISO (California) (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4139 MW
Active in queue16.3 GW41 requests
Agreement signed12.6 GW32 requests
Withdrawn10746.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
High Desert Power Plant Update
Gas
100 MWOperating San Bernardino, CACAISO Dec 20202021
Lead
Battery storage
32.7 MWOperating Kings, CACAISO Apr 2020target 2023
Re Garland
Solar
5.0 MWOperating Kern, CACAISO May 20202021
Point Wind Fast Track
Onshore wind
1.6 MWOperating Kern, CACAISO Apr 20202021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)