United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Nevada, CAISO (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown72,298 MW
Active in queue2,298 MW7 requests
Agreement signed0.0 MW0 requests
Withdrawn98,529 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bristlecone
Solar + storage
921 MWIn study Nye, NVCAISO Apr 2023target 2030
Goldlink
Solar
354 MWIn study Nye, NVCAISO Apr 2023target 2030
Serenity
Solar
305 MWIn study Nye, NVCAISO Apr 2023target 2031
Container
Solar
205 MWIn study Nye, NVCAISO Apr 2023target 2031
Grapevine 1
Solar
205 MWIn study Nye, NVCAISO Apr 2023target 2031
Nelson Hills
Solar
205 MWIn study Nye, NVCAISO Apr 2023target 2031
Nelson
Solar
104 MWIn study Nye, NVCAISO Apr 2023target 2031

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)