Interconnection queue in Nevada, CAISO (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown52,781 MW
Active in queue2,781 MW5 requests
Agreement signed1,881 MW4 requests
Withdrawn1450 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Arida 3 Solar Farm
Solar + storage
900 MWIn study Clark, NVCAISO Apr 2020target 2030
Purple Sage Energy Center
Solar + storage
817 MWAgreement signed Clark, NVCAISO Apr 2020target 2028
Rough Hat 2
Solar + storage
408 MWAgreement signed Clark, NVCAISO Apr 2020target 2027
Water Rock Solar 1
Solar + storage
400 MWAgreement signed Nye, NVCAISO Apr 2020target 2027
Delamar Energy Storage
Battery storage
256 MWAgreement signed Clark, NVCAISO Apr 2020target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)