United States › Grid › Interconnection queues › Maryland

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Maryland — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown40746.5 GW
Active in queue5,942 MW57 requests
Agreement signed1,462 MW14 requests
Withdrawn40746.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

407 requests · page 9 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AB1-052, Baltimore County
Battery storage
0.0 MWWithdrawn / abandoned Baltimore, MDPJM Aug 2015target 2015
Battery storage project AB1-039, Anne Arundel County
Battery storage
0.0 MWWithdrawn / abandoned Anne Arundel, MDPJM Aug 2015target 2015
Battery storage project AB1-020, Baltimore City County
Battery storage
0.0 MWWithdrawn / abandoned Baltimore City, MDPJM Jun 2015target 2015
Solar project W4-030, Howard County
Solar
0.0 MWWithdrawn / abandoned Howard, MDPJM Dec 2010target 2012
Battery storage project AB1-048, Baltimore County
Battery storage
0.0 MWWithdrawn / abandoned Baltimore, MDPJM Aug 2015target 2015
Battery storage project AB1-044, Howard County
Battery storage
0.0 MWWithdrawn / abandoned Howard, MDPJM Aug 2015target 2015
Battery storage project AB1-042, Anne Arundel County
Battery storage
0.0 MWWithdrawn / abandoned Anne Arundel, MDPJM Aug 2015target 2015
Page 9 of 9

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)