United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) (2023 requests) β€” page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown309110.9 GW
Active in queue110.9 GW309 requests
Agreement signed3,340 MW18 requests
Withdrawn547166.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

309 requests Β· page 7 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 441, Lewis And Clark County
Gas
12.0 MWIn study Lewis And Clark, MTWest Jan 2023target 2023
Solar project G1004, Franklin County
Solar
10.0 MWIn study Franklin, WAWest Nov 2023target 2025
Solar project G0957, Benton County
Solar
10.0 MWIn study Benton, WAWest Oct 2023target 2027
Solar + storage project 440, Lewis And Clark County
Solar + storage
4.6 MWIn study Lewis And Clark, MTWest Jan 2023target 2023
Solar project C3-148, Crook County
Solar Β· CP Prineville, LLC
3.0 MWIn study Crook, ORWest May 2023target 2033
Solar project G1003, Adams County
Solar
3.0 MWIn study Adams, WAWest Nov 2023target 2025
Solar project 454, Gallatin County
Solar
2.0 MWIn study Gallatin, MTWest Dec 2023target 2024
Solar project G0943, Snohomish County
Solar
1.0 MWIn study Snohomish, WAWest Oct 2023target 2024
Solar project G0968, Clark County
Solar
1.0 MWIn study Clark, WAWest Oct 2023target 2023
Page 7 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)