Withdrawn queue requests in Nebraska — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25545.7 GW
Active in queue16.5 GW85 requests
Agreement signed5,103 MW29 requests
Withdrawn25545.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

255 requests · page 6 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2017-241, Dawson County
Onshore wind
10.0 MWWithdrawn / abandoned Dawson, NESPP Jul 2017target 2018
Gas project GEN-2007-012N, Scotts Bluff County
Gas
8.5 MWWithdrawn / abandoned Scotts Bluff, NESPP Mar 2007
Onshore wind project GEN-2013-004, Antelope County
Onshore wind
6.0 MWWithdrawn / abandoned Antelope, NESPP Mar 2013target 2014
Onshore wind project GEN-2001-039N1, Keya Paha County
Onshore wind
5.0 MWWithdrawn / abandoned Keya Paha, NESPP Nov 2001
Onshore wind project GEN-2017-085, Saline County
Onshore wind
0.6 MWWithdrawn / abandoned Saline, NESPP May 20172023
Page 6 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)