🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in California — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21581.7 GW
Active in queue179.2 GW464 requests
Agreement signed81.7 GW215 requests
Withdrawn2,138571.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

215 requests · page 5 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Little Bear 3
Solar + storage
40.4 MWAgreement signed Fresno, CACAISO Apr 20152020
Rio Bravo Solar 1
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Apr 20122016
Kettleman Solar Project (Fka Kettleman Solar Farm)
Solar + storage
40.0 MWAgreement signed Kings, CACAISO May 20102015
Little Bear Solar 1
Solar + storage
40.0 MWAgreement signed Fresno, CACAISO Apr 20142020
Little Bear Solar 2
Solar + storage
40.0 MWAgreement signed Fresno, CACAISO Apr 20142020
Rio Bravo Solar 2
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Apr 20132016
Pumpjack Solar I (Aka Pioneer Solar I)
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Sep 20102015
Crow Creek Solar 1 (Fka: Frontier Solar 1) (Fka As Scatec Westside Solar Ranch I And Stanislaus PV - Phase 1)
Solar + storage
40.0 MWAgreement signed Stanislaus, CACAISO Dec 20092016
Starlight Solar
Solar + storage
37.4 MWAgreement signed San Diego, CACAISO May 2017target 2027
Escondido Energy Center 2
Battery storage
33.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2030
Dynamo Solar
Solar
24.5 MWAgreement signed Napa, CACAISO Apr 2019target 2027
Lake Alpaugh Battery Storage
Battery storage
10.0 MWAgreement signed Tulare, CACAISO Apr 2015target 2026
Altamont Midway LTD
Onshore wind
5.0 MWAgreement signed Alameda, CACAISO Apr 2015target 2027
Lassen Lodge Hydroelectric
Hydro
4.5 MWAgreement signed Tehama, CACAISO Mar 2011target 2027
Lassen Lodge Hydroelectric 2
Hydro
0.5 MWAgreement signed Tehama, CACAISO Apr 2013target 2027
Page 5 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)