United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2022 requests) โ page 37
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project SGI-PNM-2022-18, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-29, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-17, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-26, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-28, Valencia County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-30, San Miguel County Solar |
5.0 MW | Withdrawn / abandoned |
| Battery storage project 570148, Caldwell County Battery storage |
5.0 MW | Withdrawn / abandoned |
| Canton 470 - EMA ASO Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-27, Valencia County Solar |
5.0 MW | Withdrawn / abandoned |
| Holliston 130 - EMA ASO Battery storage |
5.0 MW | Withdrawn / abandoned |
| Solar project AH2-362, Franklin County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AH2-361, Westmoreland County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-201, Cumberland County Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-19, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-08, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-09, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AH2-321, York County Solar |
5.0 MW | Withdrawn / abandoned |
| Tremont 713 - EMA ASO Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project AH2-359, Somerset County Solar |
5.0 MW | Withdrawn / abandoned |
| Cumberland 22B - WMA ASO Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-10, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Hyannis 961 - EMA ASO Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project AH2-316, Somerset County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-22, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-202, Hunterdon County Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-25, Bernalillo County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-254, Mercer County Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Uxbridge Substation โรรฌ NG Hopedale West Group Study Battery storage |
5.0 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-23, Luna County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-179 Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project AI1-200, Lawrence County Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project AH2-134, Kanawha County Solar |
5.0 MW | Withdrawn / abandoned |
| Whitins Pond Substation โรรฌ NG Hopedale West Group Study Battery storage |
4.9 MW | Withdrawn / abandoned |
| Whitins Pond Substation โรรฌ NG Hopedale West Group Study Battery storage |
4.9 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-31, Luna County Solar |
4.8 MW | Withdrawn / abandoned |
| Marshfield 739 - EMA ASO Solar + storage |
4.6 MW | Withdrawn / abandoned |
| Sandwich 916 - EMA ASO Solar + storage |
4.6 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-24, Valencia County Solar |
4.2 MW | Withdrawn / abandoned |
| Wellfleet 976 - EMA ASO Solar + storage |
4.1 MW | Withdrawn / abandoned |
| Harwich 968 - EMA ASO Solar + storage |
4.0 MW | Withdrawn / abandoned |
| Hopkinton 126 - EMA ASO Solar + storage |
3.9 MW | Withdrawn / abandoned |
| Solar project SGI-PNM-2022-11, Luna County Solar |
3.9 MW | Withdrawn / abandoned |
| Valley 715 - EMA ASO Solar + storage |
3.7 MW | Withdrawn / abandoned |
| Falmouth 933 - EMA ASO Solar + storage |
3.5 MW | Withdrawn / abandoned |
| Solar + storage project AH2-176 Solar + storage |
3.0 MW | Withdrawn / abandoned |
| Solar project C2-87, Linn County Solar |
3.0 MW | Withdrawn / abandoned |
| Solar + storage project C2-103, Sherman County Solar + storage |
3.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-180 Solar + storage |
3.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-182, Rockingham County Solar + storage |
3.0 MW | Withdrawn / abandoned |
| Solar project C2-102, Sherman County Solar |
3.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)494 ยท 132.6 GW
- MISO (Midcontinent)567 ยท 94.5 GW
- NYISO (New York)165 ยท 57.3 GW
- Southeast (non-ISO utilities)211 ยท 28.0 GW
- SPP (Southwest Power Pool)91 ยท 19.4 GW
- PJM (Mid-Atlantic, Midwest)182 ยท 19.3 GW
- ERCOT (Texas)76 ยท 15.5 GW
- ISO-NE (New England)98 ยท 12.0 GW
- CAISO (California)2 ยท 377 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)