United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Florida (2022 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown544,026 MW
Active in queue4,026 MW54 requests
Agreement signed75.0 MW1 requests
Withdrawn473,356 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

54 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 428, Manatee County
Solar Β· FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2026
Solar project 311, Alachua County
Solar Β· Florida Renewable Partners, LLC
74.5 MWPaused / redesign Alachua, FLSoutheast May 2022target 2025
Solar project 427, Indian River County
Solar Β· FPL
74.5 MWIn study Indian River, FLSoutheast Mar 2022target 2027
Solar project 474, Desoto County
Solar Β· FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)