United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Colorado (2024 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5914.0 GW
Active in queue14.0 GW59 requests
Agreement signed666 MW3 requests
Withdrawn5566 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

59 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GI-2024-07, Pueblo County
Solar + storage
100 MWIn study Pueblo, COWest May 2024target 2028
Battery storage project GI-TC-2024-18, Montezuma County
Battery storage
100 MWIn study Montezuma, COWest May 2024target 2027
Solar project GI-2024-17, Alamosa County
Solar
100 MWIn study Alamosa, COWest May 2024target 2030
Solar project BHCT G52, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jun 2024target 2026
Solar project GI-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Apr 2024target 2028
Solar project 5RSC-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jan 2024target 2028
Battery storage project BHCT G50, Pueblo County
Battery storage Β· Black Hills Colorado Electric, LLC
50.0 MWIn study Pueblo, COWest Jun 2024target 2026
Battery storage project GI-2024-08, Pueblo County
Battery storage
10.0 MWIn study Pueblo, COWest May 2024target 2026
Solar project 24-10021, Larimer County
Solar
10.0 MWIn study Larimer, COWest Oct 2024target 2026
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)