Withdrawn queue requests in the USA (2011 requests) โ€” page 16

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown808106.0 GW
Active in queue4,539 MW21 requests
Agreement signed2,971 MW15 requests
Withdrawn808106.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

808 requests ยท page 16 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project X2-024, Salem County
Solar
2.0 MWWithdrawn / abandoned Salem, NJPJM May 2011target 2011
Washington County Renewable Energy Project
Other
2.0 MWWithdrawn / abandoned Washington, MDPJM Jun 2011target 2013
Lower Township, NJ
Solar
2.0 MWWithdrawn / abandoned Cape May, NJPJM Apr 2011target 2014
Solar project W4-079, Hunterdon County
Solar
2.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2011target 2011
Solar project X3-067, Queen Anne's County
Solar
2.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2011target 2012
Solar project GI-2011-5, Boulder County
Solar
2.0 MWWithdrawn / abandoned Boulder, COWest Jul 2011target 2012
Solar project X2-056, Cumberland County
Solar
1.9 MWWithdrawn / abandoned Cumberland, NJPJM Jun 2011target 2012
Solar project X1-091, Cumberland County
Solar
1.9 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2011target 2012
Solar project X1-003, Warren County
Solar
1.9 MWWithdrawn / abandoned Warren, NJPJM Feb 2011target 2012
Solar project X1-092, Cumberland County
Solar
1.9 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2011target 2012
Solar project X3-024, Cape May County
Solar
1.8 MWWithdrawn / abandoned Cape May, NJPJM Aug 2011target 2012
Solar project X3-025, Warren County
Solar
1.8 MWWithdrawn / abandoned Warren, NJPJM Aug 2011target 2012
Edgewood
Solar
1.8 MWWithdrawn / abandoned Hancock, OHPJM Aug 2011target 2014
Solar project X2-095, Cape May County
Solar
1.8 MWWithdrawn / abandoned Cape May, NJPJM Jul 2011target 2012
Solar project X1-111, Ocean County
Solar
1.6 MWWithdrawn / abandoned Ocean, NJPJM Apr 2011target 2011
Onshore wind project 405, Tooele County
Onshore wind ยท Tasco Energy, LLC
1.6 MWWithdrawn / abandoned Tooele, UTWest Oct 2011target 2013
Other project 368, Douglas County
Other
1.6 MWWithdrawn / abandoned Douglas, ORWest Jan 2011target 2011
Hydro project 395, Deschutes County
Hydro
1.6 MWWithdrawn / abandoned Deschutes, ORWest Jul 2011target 2013
Other project 386, Polk County
Other
1.6 MWWithdrawn / abandoned Polk, ORWest Apr 2011target 2012
Solar project W4-089, Cumberland County
Solar
1.6 MWWithdrawn / abandoned Cumberland, NJPJM Jan 2011target 2011
Solar project X2-081, Warren County
Solar
1.5 MWWithdrawn / abandoned Warren, NJPJM Jul 2011target 2012
Hydro project 391, Deschutes County
Hydro ยท Ormat Nevada, Inc.
1.4 MWWithdrawn / abandoned Deschutes, ORWest Jun 2011target 2013
Renaissance at Hanover Solar Farm
Solar
1.3 MWWithdrawn / abandoned Morris, NJPJM Mar 2011target 2014
Calrenew-1 Expansion
Solar
1.3 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2013
Solar project W4-090, Cumberland County
Solar
1.3 MWWithdrawn / abandoned Cumberland, NJPJM Jan 2011target 2011
Other project 383, Twin Falls County
Other
1.2 MWWithdrawn / abandoned Twin Falls, IDWest Jul 2011
Other project 372, Ada County
Other
1.1 MWWithdrawn / abandoned Ada, IDWest Apr 2011
Solar project W4-048, Essex County
Solar
1.1 MWWithdrawn / abandoned Essex, NJPJM Jan 2011target 2011
Solar project X1-066, Atlantic County
Solar
1.0 MWWithdrawn / abandoned Atlantic, NJPJM Apr 2011target 2011
Solar project X1-115, Sussex County
Solar
1.0 MWWithdrawn / abandoned Sussex, NJPJM Apr 2011target 2013
Battery storage project 138, Deer Lodge County
Battery storage
1.0 MWWithdrawn / abandoned Deer Lodge, MTWest Apr 2011target 2011
Battery storage project 131, Deer Lodge County
Battery storage
1.0 MWWithdrawn / abandoned Deer Lodge, MTWest Feb 2011target 2011
Solar project X2-074, Camden County
Solar
1.0 MWWithdrawn / abandoned Camden, NJPJM Jul 2011target 2012
Hydro project 362, Lemhi County
Hydro
1.0 MWWithdrawn / abandoned Lemhi, IDWest Jan 2011
Solar project X3-026, Atlantic County
Solar
1.0 MWWithdrawn / abandoned Atlantic, NJPJM Aug 2011target 2012
Other project 364, Twin Falls County
Other
0.8 MWWithdrawn / abandoned Twin Falls, IDWest Jan 2011
Other project 365, Cassia County
Other
0.8 MWWithdrawn / abandoned Cassia, IDWest Jan 2011
Holly Ranch
Solar
0.5 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2014
Montgomery Recycling
Other
0.5 MWWithdrawn / abandoned Essex, NJPJM Apr 2011target 2012
Astra Foods
Gas
0.5 MWWithdrawn / abandoned Delaware, PAPJM Oct 2011target 2012
Hydro project 366, Lemhi County
Hydro
0.5 MWWithdrawn / abandoned Lemhi, IDWest Feb 2011
Hydro project 34, Adams County
Hydro
0.4 MWWithdrawn / abandoned Adams, WAWest Aug 2011target 2012
Solar project X2-078, Hunterdon County
Solar
0.4 MWWithdrawn / abandoned Hunterdon, NJPJM Jul 2011target 2012
Other project 390, Beaver County
Other
0.4 MWWithdrawn / abandoned Beaver, UTWest May 2011target 2011
Solar project 381, Twin Falls County
Solar
0.4 MWWithdrawn / abandoned Twin Falls, IDWest Jul 2011
Elevation Solar C
Solar
0.1 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2017
Battery storage project X4-028, Cook County
Battery storage
0.1 MWWithdrawn / abandoned Cook, ILPJM Dec 2011target 2011
Aspiration Solar E
Solar
0.1 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2015
Liberty Solar
Solar
0.1 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2016
Citizen Solar C
Solar
0.1 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)