Millour Hill
Millour Hill is a 18 MW onshore wind farm in Scotland, operated by Community Wind Power. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Scotland
Key facts
- Installed capacity
- 18 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Community Wind Power
- Region
- Scotland
- Country
- Scotland
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Coordinates
- 55.7307, -4.7750
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Millour Hill compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 18 MW station would generate roughly 41 GWh of electricity in a year, similar to the annual use of about 15,180 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Scotland All run by Community Wind PowerNearby generating sites
- Millour Hill Ext. Β· 6.4 MW onshore wind farm0.4 km
- Wardlaw Wood Β· 18 MW onshore wind farm1.3 km
- Kelburn Wind Farm (GB) Β· 28 MW onshore wind farm3.4 km
- Sorbie Β· 12.6 MW onshore wind farm7.0 km
- Hunterston A Β· 300 MW nuclear power station7.3 km
- Hunterston B Β· 980 MW nuclear power station7.3 km
- Torness Β· 1,200 MW nuclear power station7.6 km
- Lochcraigs Farm Β· 4.99 MW solar farm8.4 km
Also operated by Community Wind Power
Community Wind Power operates 8 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Millour Hill Community Windfarm
- Developer / operator
- Community Windpower
- Planning authority
- North Ayrshire
- Planning reference
- 09/00424/PPM
- Application submitted
- 25 June 2009
- Permission granted
- 16 December 2009
- Construction started
- 1 April 2011
- Began operating
- 1 May 2012
- Capacity in planning record
- 18 MW
- Address
- Baidland Hill,, Strathclyde
- REPD reference
- 3690
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.