Butterwick Moor Circuit 1 is a 9.4 MW onshore wind farm in North East England, operated by RWE Npower. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • North East
  • England
Project stageOperating
  1. PlanningJan 2007 (completed)
  2. ConsentedJun 2007 (completed)
  3. ConstructionSep 2010 (completed)
  4. OperatingApr 2011 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
9.4 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
RWE Npower
Region
North East
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
TS21 3ER
Coordinates
54.6636, -1.3969

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Butterwick Moor Circuit 1 compares

343rd of 488largest wind farms in the UK register
17th of 41in North East
0.03%of listed UK wind farms capacity
β‰ˆ 21 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 9.4 MW station would generate roughly 21 GWh of electricity in a year, similar to the annual use of about 7,930 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in North East All run by RWE Npower

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Butterwick Moor
Developer / operator
E.ON UK
Planning authority
County Durham
Planning reference
7/2006/0796/DM
Application submitted
2 January 2007
Permission granted
17 June 2007
Construction started
1 September 2010
Began operating
1 April 2011
Capacity in planning record
20.5 MW
Address
Butterwick Moor , Sedgefield, County Durham
REPD reference
3218

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.