Clyde Wind farm, Lowther Hills, between Crawford and Nether Howecleuch,
NW of Lockerbie, Strathclyde
Clyde Wind Farm is a 350 MW onshore wind project in Scotland. The applicant or operator on record is Scottish and Southern Energy (SSE)/ Greencoat UK Wind. It is recorded as operational since October 2012. The determining authority is Scottish Government (S36).β¦
OperationalΒ· Since 2012
Project stageOperating
PlanningOct 2004 (completed)
ConsentedJul 2008 (completed)
Construction (completed)
OperatingOct 2012 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2018-06-01.
Registered planning capacity; not measured generation.
Clyde Wind Farm is a 350 MW onshore wind project in Scotland. The applicant or operator on record is Scottish and Southern Energy (SSE)/ Greencoat UK Wind. It is recorded as operational since October 2012. The determining authority is Scottish Government (S36).
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
350.000 MW
No. of turbines/units
152
Unit capacity
2.3 MW each
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Scottish and Southern Energy (SSE)/ Greencoat UK Wind
Owner / operator
Scottish and Southern Energy (SSE)/ Greencoat UK Wind
Year consented
2008
Commissioned / target
2012
Location
Clyde Wind farm, Lowther Hills, between Crawford and Nether Howecleuch,
NW of Lockerbie, Strathclyde