Eastern Green Link 1 (Torness–Hawthorn Pit)

Under construction

Onshore construction was announced in February 2025. EGL1 connects the Torness area to Hawthorn Pit over a predominantly subsea route of more than 190 km. It is distinct from EGL2 and does not terminate at Drax.

Sources reviewed 2026-10-08 · SP Energy Networks / National Grid

Project facts

StatusUnder construction
Developer / operatorSP Energy Networks / National Grid
RegionEast Lothian / County Durham
CountryUnited Kingdom
Published rating2,000 MW
Rating definitionTransfer capacity
Connection / routeTorness area ↔ Hawthorn Pit, County Durham
Delivery target2029 (developer target; subject to change)
Voltage525 kV

What this link contributes

This asset provides a route for electricity to move between networks or strengthens the network carrying that electricity. Its capacity cannot be added to wind, solar or power-station capacity as though it were another generator.

Torness area ↔ Hawthorn Pit, County Durham

Converter stations, cable manufacture, offshore installation, landfall works and grid energisation can progress at different times. The status above describes the documented project stage rather than assuming all work packages are complete.

Project location

Connection sites and areas are shown separately. Dashed circles mark approximate endpoint areas. No straight line is presented as the cable or overhead-line route.

Loading OpenStreetMap…

Markers identify sites, published points or labelled connection areas. Markers are not site boundaries or entrances. EGL2’s additional outlines and route layers are explicitly identified in the developer’s map data.

Sources and review date

  1. SP Energy Networks / National Grid project information
    Reviewed 2026-10-08

How Octary distinguishes proposals, published ratings and live measurements

Report a correction with a source

GRID CONTEXT

Great Britain electricity now

Explore the grid →
Loading the latest published grid interval…

National figures from the Carbon Intensity API. These do not measure an individual project’s output, cable flow or data-centre electricity use.