Project facts
| Status | In planning |
|---|---|
| Developer / operator | Apatura |
| Region | Falkirk |
| Country | Scotland |
| Published rating | 300 MW |
| Rating definition | Proposed campus capacity |
| Connection / route | Confirmed grid connections claimed by developer; public energisation evidence pending |
| Delivery target | 2028 (developer target; subject to change) |
Electricity demand and supply
| IT capacity | Not published |
|---|---|
| Grid connection capacity | Not published |
| Apparent power reservation / substation rating | Not published |
| Measured average electricity demand | Not published |
| Published annual electricity consumption | Not published |
| Power usage effectiveness (PUE) | Not published |
Where its electricity comes from
Grid supply. Site-specific renewable contracts, private-wire supply and annual consumption have not been confirmed in the reviewed source.
Cooling, water and backup power
Cooling and water-use figures have not been independently confirmed.
Backup capacity and fuel are not quantified in this profile.
Rated capacity is not present consumption. Renewable procurement claims describe contracts or certificates unless hourly matching and physical supply are evidenced. No live site meter is connected to this page.
Project location
This point is published in the developerβs consultation map. It identifies the project location, not a surveyed boundary or a public entrance.
Loading OpenStreetMapβ¦
- Larbert Data Centre Campus β developer map point Developer-published location Open larger map Location source 56.03083, -3.83944 Β· WGS84
Markers identify sites, published points or labelled connection areas. Markers are not site boundaries or entrances. EGL2βs additional outlines and route layers are explicitly identified in the developerβs map data.
Sources and review date
- Larbert proposed design
Reviewed 2026-10-08 - Planning application and 2028 target
Reviewed 2026-10-08