Railroad Energy Center, LLC

Railroad Energy Center, LLC is a 20.0 MW under construction battery storage site in Prince William County, Virginia, operated by East Point Energy, LLC.

Plant statusUnder construction
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Planned start of operation reported to EIA: Dec 2026.

Open in Google MapsMore battery storage sites in Virginia

Generators

Each generating unit EIA lists at this plant.

UnitTechnologyCapacityStatusOnlineRetired / planned retirement
RAILRBatteries20 MW Under construction (up to 50%)Target Dec 2026

Plant details

Operator
East Point Energy, LLC
Location
Prince William County, Virginia
Balancing authority
PJM
Sector
IPP Non-CHP
Capacity
Under construction: 20.0 MW
EIA plant ID
70233

Location

38.7817, -77.5420

Nearby power plants

Source: U.S. Energy Information Administration, Form EIA-860M, September 2026. Planned dates are targets reported by the developer and often change. Report a problem