MCCo BESS Generating Facility

MCCo BESS Generating Facility is a 19.2 MW operating power plant in Cuyahoga County, Ohio, operated by The Medical Center Company.

Plant statusOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2012 (current stage)
  5. Closed (not yet reached)

This plant has generators at more than one stage; see the table below.

Open in Google MapsMore battery storage sites in Ohio

Generators

Each generating unit EIA lists at this plant.

UnitTechnologyCapacityStatusOnlineRetired / planned retirement
B020Petroleum Liquids1.8 MW Standby / back-upOct 2012
B021Petroleum Liquids1.8 MW Standby / back-upOct 2012
1Batteries3.9 MW Under construction (over 50%)Target Oct 2026
2Batteries3.9 MW Under construction (over 50%)Target Oct 2026
3Batteries3.9 MW Under construction (over 50%)Target Oct 2026
4Batteries3.9 MW Under construction (over 50%)Target Oct 2026

Plant details

Operator
The Medical Center Company
Location
Cuyahoga County, Ohio
Balancing authority
PJM
Sector
IPP Non-CHP
Capacity
Operating: 3.6 MW
Under construction: 15.6 MW
First unit online
Oct 2012
EIA plant ID
69593

Location

41.3026, -81.3604