United States › Power plants › Bioenergy plants › California
BIOENERGY PLANTSGodinho Dairy Digester
Godinho Dairy Digester is a 2.0 MW operating bioenergy plant in Merced County, California, operated by Aligned Digesters Co., LLC.
Generators
Each generating unit EIA lists at this plant.
| Unit | Technology | Capacity | Status |
|---|---|---|---|
| GEN1 | Other Waste Biomass | 1.0 MW | |
| GEN2 | Other Waste Biomass | 1.0 MW |
Plant details
- Operator
- Aligned Digesters Co., LLC
- Location
- Merced County, California
- Balancing authority
- CISO
- Sector
- IPP Non-CHP
- Capacity
- Operating: 2.0 MW
- First unit online
- Jan 2026
- EIA plant ID
- 68837
Location
37.1074, -120.8591
Nearby power plants
- Merced 1 PVSolar farms · 3.0 MW · 8.2 mi
- Merced BESSBattery storage · 3.0 MW · 8.2 mi
- Lara 2 HybridSolar farms, Battery storage · 1.6 MW · 8.2 mi
- Wright Solar ParkSolar farms · 200 MW · 8.7 mi
- Stellar Wright BESSBattery storage · 84.8 MW · 9.0 mi
- ONeillHydroelectric plants · 25.2 MW · 10.4 mi
- Quinto Solar PV ProjectSolar farms · 108 MW · 10.8 mi
- Sun Harvest Solar NDP1Solar farms · 1.5 MW · 11.8 mi
- W R GianelliHydroelectric plants · 424 MW · 12.3 mi
- Dos Palos Cooperative GinSolar farms · 1.0 MW · 12.5 mi
Source: U.S. Energy Information Administration, Form EIA-860M, September 2026. Planned dates are targets reported by the developer and often change. Report a problem