United States › Power plants › Hydroelectric plants › Washington

HYDROELECTRIC PLANTS

Chief Joseph

Chief Joseph is a 2,280 MW operating hydroelectric plant in Douglas County, Washington, operated by USACE Northwestern Division.

Plant statusOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 1955 (current stage)
  5. Closed (not yet reached)

This plant has generators at more than one stage; see the table below.

Open in Google MapsMore hydroelectric plants in Washington

Generators

Each generating unit EIA lists at this plant.

UnitTechnologyCapacityStatusOnlineRetired / planned retirement
17Conventional Hydroelectric95 MW OperatingJul 1977
18Conventional Hydroelectric95 MW OperatingAug 1977
19Conventional Hydroelectric95 MW Out of service, expected to returnNov 1977
20Conventional Hydroelectric95 MW OperatingJun 1978
21Conventional Hydroelectric95 MW OperatingJun 1978
22Conventional Hydroelectric95 MW OperatingJun 1978
23Conventional Hydroelectric95 MW OperatingSep 1978
24Conventional Hydroelectric95 MW OperatingJan 1979
25Conventional Hydroelectric95 MW OperatingJan 1979
26Conventional Hydroelectric95 MW OperatingFeb 1979
27Conventional Hydroelectric95 MW OperatingMay 1979
1Conventional Hydroelectric88 MW OperatingOct 1958
2Conventional Hydroelectric88 MW OperatingJul 1958
3Conventional Hydroelectric88 MW OperatingMay 1958
4Conventional Hydroelectric88 MW OperatingFeb 1958
5Conventional Hydroelectric88 MW OperatingFeb 1957
6Conventional Hydroelectric88 MW OperatingDec 1956
7Conventional Hydroelectric88 MW Out of service long-termNov 1956
8Conventional Hydroelectric88 MW Out of service long-termSep 1956
9Conventional Hydroelectric88 MW Out of service, expected to returnDec 1955
10Conventional Hydroelectric88 MW Out of service, expected to returnSep 1955
11Conventional Hydroelectric88 MW Out of service, expected to returnSep 1955
12Conventional Hydroelectric88 MW Out of service, expected to returnSep 1955
13Conventional Hydroelectric88 MW Out of service, expected to returnFeb 1957
14Conventional Hydroelectric88 MW OperatingJul 1957
15Conventional Hydroelectric88 MW OperatingSep 1957
16Conventional Hydroelectric88 MW OperatingNov 1957

Plant details

Operator
USACE Northwestern Division
Location
Douglas County, Washington
Balancing authority
BPAT
Sector
Electric Utility
Capacity
Operating: 2,280 MW
Out of service: 176 MW
First unit online
Sep 1955
EIA plant ID
3921

Location

47.9951, -119.6404

Nearby power plants