United States › Power plants › Gas power plants › New Jersey

GAS POWER PLANTS

Kearny Generating Station

Kearny Generating Station is a 605 MW operating gas power plant in Hudson County, New Jersey, operated by Parkway Generation Operating, LLC.

Plant statusOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 1953 (current stage)
  5. ClosedAug 2014 (not yet reached)

This plant has generators at more than one stage; see the table below.

Open in Google MapsMore gas power plants in New Jersey

Generators

Each generating unit EIA lists at this plant.

UnitTechnologyCapacityStatusOnlineRetired / planned retirement
131Natural Gas Fired Combustion Turbine61 MW OperatingJun 2012
132Natural Gas Fired Combustion Turbine61 MW OperatingJun 2012
133Natural Gas Fired Combustion Turbine61 MW OperatingJun 2012
134Natural Gas Fired Combustion Turbine61 MW OperatingJun 2012
141Natural Gas Fired Combustion Turbine61 MW OperatingJun 2012
142Natural Gas Fired Combustion Turbine61 MW OperatingJun 2012
N121Natural Gas Fired Combustion Turbine61 MW OperatingAug 2001
N122Natural Gas Fired Combustion Turbine61 MW OperatingAug 2001
N123Natural Gas Fired Combustion Turbine61 MW OperatingAug 2001
N124Natural Gas Fired Combustion Turbine61 MW OperatingAug 2001
7Petroleum Liquids147 MW RetiredMar 1953Jun 2005
8Petroleum Liquids147 MW RetiredJan 1953Jun 2005
10Natural Gas Fired Combustion Turbine146 MW RetiredMay 1970Jun 2012
11Natural Gas Fired Combustion Turbine146 MW RetiredDec 1969Jun 2012
9Natural Gas Fired Combustion Turbine19 MW RetiredMay 1967Aug 2014

Plant details

Operator
Parkway Generation Operating, LLC
Location
Hudson County, New Jersey
Balancing authority
PJM
Sector
IPP Non-CHP
Capacity
Operating: 605 MW
Retired: 605 MW
First unit online
Jan 1953
EIA plant ID
2404

Location

40.7373, -74.0965

Nearby power plants