United States › Power plants › Bioenergy plants › California
BIOENERGY PLANTSMarina Landfill Gas
Marina Landfill Gas is a 11.5 MW operating bioenergy plant in Monterey County, California, operated by Monterey Regional Waste Mgmt.
Generators
Each generating unit EIA lists at this plant.
| Unit | Technology | Capacity | Status |
|---|---|---|---|
| U1C06 | Landfill Gas | 1.6 MW | |
| U4J16 | Landfill Gas | 1.4 MW | |
| U2J18 | Landfill Gas | 1.1 MW | |
| U3J17 | Landfill Gas | 1.0 MW | |
| FUTR1 | Landfill Gas | 1.6 MW | Planned, approvals not yet sought |
| FUTR2 | Landfill Gas | 1.6 MW | Planned, approvals not yet sought |
| FUTR3 | Landfill Gas | 1.6 MW | Planned, approvals not yet sought |
| FUTR4 | Landfill Gas | 1.6 MW | Planned, approvals not yet sought |
| U4J08 | Landfill Gas | 1.4 MW | Retired |
| U2J02 | Landfill Gas | 1.0 MW | Retired |
| U3J98 | Landfill Gas | 1.0 MW | Retired |
| G4 | Landfill Gas | 0.9 MW | Retired |
| U3J16 | Landfill Gas | 0.9 MW | Retired |
| LL1 | Landfill Gas | 0.8 MW | Retired |
Plant details
- Operator
- Monterey Regional Waste Mgmt
- Location
- Monterey County, California
- Balancing authority
- CISO
- Sector
- Commercial Non-CHP
- Capacity
- Operating: 5.1 MW
Planned: 6.4 MW
Retired: 6.0 MW - First unit online
- Apr 1994
- EIA plant ID
- 10748
Location
36.7131, -121.7686
Nearby power plants
- Monterey One WaterBioenergy plants · 1.8 MW · 0.5 mi
- Monterey Regional Water Pollution ControSolar farms · 1.0 MW · 1.2 mi
- Dynegy Moss Landing Power Plant HybridGas power plants, Battery storage · 1,848 MW · 6.4 mi
- Elkhorn Battery Energy Storage SystemBattery storage · 183 MW · 6.6 mi
- TLR000 Hansen Fuel CellGas power plants · 3.0 MW · 8.9 mi
- Taylor Farms - Schilling PlaceGas power plants · 1.0 MW · 9.0 mi
- D'Arrigo Brothers - Phase 4Solar farms, Battery storage · 2.2 MW · 10.0 mi
- Ameresco Santa Cruz EnergyBioenergy plants · 3.0 MW · 14.4 mi
- Graniterock QuarrySolar farms · 4.4 MW · 14.6 mi
- Hollister Wastewater FacilitySolar farms · 1.0 MW · 20.4 mi
Source: U.S. Energy Information Administration, Form EIA-860M, September 2026. Planned dates are targets reported by the developer and often change. Report a problem