United States βΊ Grid βΊ Interconnection queues βΊ New Jersey
SOLAR Β· PJMHarrison SP
Harrison SP is a 1.2 MW solar request withdrawn in the PJM interconnection queue, in Hudson County, New Jersey, connecting to PSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2009 (completed)
- Withdrawn / abandonedJan 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- V3-039
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PSEG
- Connection point (POI)
- Harrison 4kV
- Location
- Hudson County, New Jersey
- Technology
- Solar: 1.2 MW
- Total requested
- 1.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 16 September 2009
- Proposed online date
- December 2010
- Withdrawn
- January 2013
Location
Marker shows the centre of Hudson County; the queue data does not give exact sites.
Power plants in New Jersey Β· Transmission lines in New Jersey
Other requests in Hudson County
- Hudson Energy Storage FacilityBattery storage Β· 200 MW Β· agreement signed
- Two Rivers StorageBattery storage Β· 150 MW Β· agreement signed
- Bayonne Energy CenterGas Β· 500 MW Β· built
- Bayonne Energy CenterGas Β· 500 MW Β· built
- Kearny #13Gas Β· 178 MW Β· built
- Kearny #12Gas Β· 168 MW Β· built
- Bayonne Energy Center IIGas Β· 129 MW Β· built
- Bayonne Energy Center IIGas Β· 129 MW Β· built
- Kearny #14Gas Β· 89.0 MW Β· built
- Kearny Generating StationGas Β· 40.0 MW Β· built
- Hudson Generating StationCoal Β· 24.0 MW Β· built
- Kearny Generating StationGas Β· 24.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem