🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

St. Lawrence Wind Farm II

St. Lawrence Wind Farm II is a 80.0 MW onshore wind request withdrawn in the NYISO interconnection queue, in Jefferson County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2005 (completed)
  2. Withdrawn / abandonedJun 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
167
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
AES NY Wind, LLC
Connection point (POI)
Lyme Substation
Location
Jefferson County, New York
Technology
Wind: 80.0 MW
Total requested
80.0 MW
Queue status
Withdrawn
Entered queue
8 February 2005
Withdrawn
June 2019

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem