BATTERY STORAGE Β· ERCOT

Hearn Road BESS

Hearn Road BESS is a 9.9 MW battery storage request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jun 2023 (completed)
  2. ConsentedJun 2024 (completed)
  3. Construction (completed)
  4. OperatingAug 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0596
Grid region
ERCOT (Texas)
Developer
Regis Hearn, LLC
Connection point (POI)
Station Name (TSP Station Code): Hearn Road(5021)_x000D_ Load/Load Transformer Name: R2_x000D_ PTI Bus Number: 8860_x000D_ Voltage in kV (Transmission Level): 69kV
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
MRD Approved
Queue status
Operational
Entered queue
27 June 2023
Agreement signed
21 June 2024
Proposed online date
August 2025
Came online
August 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem