United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

SOLAR Β· NYISO

Dexter Solar

Dexter Solar is a 19.8 MW solar request withdrawn in the NYISO interconnection queue, in Jefferson County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2021 (completed)
  2. Withdrawn / abandonedJul 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1195
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Dexter Solar, LLC
Connection point (POI)
Dexter 23 kV Substation
Location
Jefferson County, New York
Technology
Solar: 19.8 MW
Total requested
19.8 MW
Queue status
Withdrawn
Entered queue
4 June 2021
Withdrawn
July 2021

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem