πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Fermi

Fermi is a 149 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jan 2010 (completed)
  2. ConsentedAug 2015 (completed)
  3. Construction (completed)
  4. OperatingOct 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
11INR0082a
Grid region
ERCOT (Texas)
Developer
Akuo Energy
Connection point (POI)
181751 & 181752 Rockspring W 34.5kV
Technology
Wind: 149 MW
Total requested
149 MW
Study phase
IA
Queue status
Operational
Entered queue
11 January 2010
Agreement signed
12 August 2015
Proposed online date
November 2017
Came online
October 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem