ONSHORE WIND Β· ERCOTGrandview W 3
Grandview W 3 is a 188 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2009 (completed)
- Withdrawn / abandonedOct 2018 (project stopped here)
- ConsentedApr 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 13INR0005c
- Grid region
- ERCOT (Texas)
- Developer
- Eon
- Connection point (POI)
- 140653 Alibates 345kV
- Technology
- Wind: 188 MW
- Total requested
- 188 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 26 March 2009
- Agreement signed
- 23 April 2014
- Proposed online date
- December 2019
- Withdrawn
- October 2018
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem