United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

SOLAR + STORAGE Β· MISO

Solar + storage project J2824, Yazoo County

Solar + storage project J2824, Yazoo County is a 70.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Yazoo County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2824
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
Picken - Midway SS (CE) 115 kV
Location
Yazoo County, Mississippi
Technology
Solar: 70.0 MW Β· Battery
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 September 2022
Proposed online date
March 2025
Withdrawn
July 2025

Location

Marker shows the centre of Yazoo County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Yazoo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem