United States › Grid › Interconnection queues › Washington
ONSHORE WIND · WESTSea Breeze Olympic Ph 3
Sea Breeze Olympic Ph 3 is a 330 MW onshore wind request withdrawn in the West interconnection queue, in Clallam County, Washington, connecting to Olympic Converter, LP - Don'T Use.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2004 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G134
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Olympic Converter, LP - Don'T Use
- Connection point (POI)
- Port Angeles 230 kV or Fairmount 230 kV
- Location
- Clallam County, Washington
- Technology
- Wind: 330 MW
- Total requested
- 330 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 7 June 2004
- Proposed online date
- May 2010
Location
Marker shows the centre of Clallam County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Clallam County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem