πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Torrecillas Wind B

Torrecillas Wind B is a 200 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedJan 2015 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
14INR0045b
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
161352, 161401 Torrecillas 34.5kV
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
30 January 2013
Agreement signed
30 January 2015
Proposed online date
December 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem