OFFSHORE WIND Β· ERCOTGulf Offshore Wind 2
Gulf Offshore Wind 2 is a 132 MW offshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2013 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 16INR0011b
- Grid region
- ERCOT (Texas)
- Developer
- Baronyx
- Technology
- Offshore Wind: 132 MW
- Total requested
- 132 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 5 June 2013
- Proposed online date
- December 2017
Location
No county location in the queue data.