United States βΊ Grid βΊ Interconnection queues βΊ Iowa
SOLAR Β· MISOSolar project J998, Dallas County
Solar project J998, Dallas County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Dallas County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedMar 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J998
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY COMPANY
- Connection point (POI)
- Adel - Waukee 69kV Line Tap
- Location
- Dallas County, Iowa
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Proposed online date
- September 2020
- Withdrawn
- March 2020
Location
Marker shows the centre of Dallas County; the queue data does not give exact sites.
Other requests in Dallas County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem