Cody Road Wind Farm

Cody Road Wind Farm is a 10.5 MW onshore wind request withdrawn in the NYISO interconnection queue, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
131
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Green Power Energy, LLC
Connection point (POI)
Oneida-Cortland line
Location
New York
Technology
Wind: 10.5 MW
Total requested
10.5 MW
Queue status
Withdrawn
Entered queue
5 March 2003

Location

No county location in the queue data.

Power plants in New York Β· Transmission lines in New York

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem